Pillar: Buying building land in France

Building permit in France: processing times, missing documents and tacit approval

Planning and permits·16 min read·Updated 12 November 2026

In France, if no document is requested and no extension notified within a month of filing, the town hall (mairie) has, as a rule, two months to decide on a building permit for a single house; after that, its silence amounts, with some exceptions, to a tacit permit (Planning Code, art. R423-23 and R424-1). First step: keep the filing receipt, which gives the date of that tacit permit.

In brief

  • 1, 2 or 3 months. Prior declaration: 1 month; building permit for a single house: 2 months; other building permits and development permits: 3 months, from a complete file. Within a month of filing, the mairie (town hall) may ask for documents or extend the period, for example by one month near a listed historic monument; with no letter in that month, no extension applies, apart from exceptional ones (art. R423-34 to R423-37-3).
  • Missing documents: three months. If not every document has reached the town hall three months after you received the letter, the application is tacitly refused. Otherwise the period runs from their receipt.
  • Silence means yes, with exceptions. A building on the historic monuments register, a classified site, a public inquiry, an environmental assessment, an unfavourable or conditional opinion from the ABF heritage architect: in these cases and the others listed below, silence means refusal.
  • After approval. Third-party appeals: two months from the first day of two months of continuous display on the land. Withdrawal of an unlawful permit: three months after the decision. Validity: three years as a general rule, extendable twice by a year under conditions; a transitional regime applies to permits from 2021 to May 2024.
On this page

Standard periods and when they start

The standard period is one month for a déclaration préalable (prior declaration, the lighter procedure for small works), two months for a permis de construire (building permit) for a single house or its outbuildings and for a demolition permit, and three months for other building permits and development permits (art. R423-23). It runs from the day the town hall receives a complete file (art. R423-19), and the file counts as complete if no list of missing documents has been notified within a month of filing (art. R423-22).

You file at the town hall of the commune where the land is, by hand or by recorded delivery. Communes of more than 3,500 inhabitants have an online procedure for applications filed since 1 January 2022 (art. L423-3); elsewhere it depends on the commune. Service-Public’s assistant (in French) lists the documents to attach. Cost: recorded delivery, and the drawings on a quote. The receipt (récépissé) gives the file number and the date on which the permit becomes tacit (art. R423-4): keep it.

ApplicationStandard periodSilence at the end
Prior declaration1 month (R423-23 a)Tacit non-opposition (R424-1 a), except R424-2 II and R424-2-1
Building permit, single house or outbuildings2 months (R423-23 b)Tacit permit (R424-1 b), except R424-2, R424-2-1 and R424-3
Other building permits, development permits3 months (R423-23 c)Tacit permit, same exceptions

Standard periods, before any extension. Sources: Planning Code, art. R423-19 to R423-37-3 (processing periods); Planning Code, art. R424-1 to R424-4 (tacit decisions). Accessed 12 November 2026.

When the period gets longer

The period is extended in the cases the Code lists. The town hall must tell you within a month of filing the new period, its starting point and the reasons (art. R423-42); an extension not notified in this way does not apply (art. R423-43).

SituationEffectArticle
Another body of law applies; exemption (1° and 3° of art. L152-4 and L152-6); protected heritage area or surroundings of historic monuments; opinion of the CDPENAF farmland commission; public participation (Environment Code art. L123-19-2, or R423-58-1); building subject to demolition (art. L121-22-5, I)+1 month, prior declarations includedR423-24
Permits: departmental or regional commission; agriculture minister (Rural Code L643-4); exemption under Rural Code L111-3 or Construction Code L111-4-1; retail licence; online public participation (also for a declaration). Not added to the +1 month+2 monthsR423-25
Declaration referred to the regional heritage and architecture commission+2 monthsR423-25-1
Core of a national park; national commission; Corsican Assembly; national nature reserve (declaration: 2 months); building on the monuments register; public-access building or high-rise5 monthsR423-26 to R423-28
Prior woodland clearance; defence or civil aviation; special consent under the protected-sites law3 to 10 months depending on the caseR423-29 to R423-31
Public inquiry (other than woodland clearance); bringing a planning document into line2 months or 1 month after the report or decisionR423-20, R423-21, R423-32, R423-32-1
Exceptional extensions, notified before the initial period ends (R423-44): woodland clearance, dispute with the ABF taken to the prefect, call-in by a minister, cinema, retail; suspensions (European Commission, consultation, impact study)+2 to 5 months, 8 months, or suspensionR423-34 to R423-37-3

The extensions of R423-24 and R423-25 are not added to the periods of R423-26 to R423-32-1 (art. R423-33). Sources: Planning Code, art. R423-19 to R423-37-3 (processing periods). Accessed 12 November 2026.

Processing period by situation, in months (Planning Code)Prior declaration: 1 month. Building permit for a single house: 2 months; 3 months near a listed historic monument or in a protected heritage area, if the CDPENAF farmland commission must give an opinion or another body of law applies; 4 months if another departmental or regional commission is consulted; 5 months for a building on the historic monuments register or in the core of a national park; 8 months with a special consent under the protected-sites law. In the last three cases, silence at the end of the period means refusal.Silence at the end: tacit approval, with exceptionsSilence at the end: refusalPrior declarationgeneral case (R423-23 a)1 monthPermit, single housegeneral case (R423-23 b)2 monthsHouse near a historic monument,heritage area, CDPENAF (R423-24)3 monthsHouse: other departmentalor regional commission (R423-25 a)4 monthsBuilding on the monuments register(R423-28 a, R424-2 c)5 monthsCore of a national park(R423-26, R424-2 f)5 monthsSpecial consent, protected sites(R423-31 c, R424-2 a)8 monthsNear a historic monument: no tacit permit if the ABF has notified an unfavourable opinion or one with conditions(R424-3).
Processing period by situation, in months (Planning Code)Prior declaration: 1 month. Building permit for a single house: 2 months; 3 months near a listed historic monument or in a protected heritage area, if the CDPENAF farmland commission must give an opinion or another body of law applies; 4 months if another departmental or regional commission is consulted; 5 months for a building on the historic monuments register or in the core of a national park; 8 months with a special consent under the protected-sites law. In the last three cases, silence at the end of the period means refusal.Silence at the end: tacit approval, with exceptionsSilence at the end: refusalPrior declarationgeneral case (R423-23 a)1 monthPermit, single housegeneral case (R423-23 b)2 monthsHouse near a historic monument,heritage area, CDPENAF (R423-24)3 monthsHouse: other departmentalor regional commission (R423-25 a)4 monthsBuilding on the monuments register(R423-28 a, R424-2 c)5 monthsCore of a national park(R423-26, R424-2 f)5 monthsSpecial consent, protected sites(R423-31 c, R424-2 a)8 monthsNear a historic monument: no tacit permit if the ABFhas notified an unfavourable opinion or one withconditions (R424-3).
Legal periods for some situations; the period for your file is the one on the receipt or in the extension letter. Sources: Planning Code, art. R423-19 to R423-37-3 (processing periods); Planning Code, art. R424-1 to R424-4 (tacit decisions). Accessed 12 November 2026. Version in force on 12/11/2026.

Missing documents: what happens exactly

If the file lacks documents the Code requires, the town hall sends you, within a month of filing, a recorded-delivery letter listing them “exhaustively” (art. R423-38). It counts as received when first presented (art. R423-47), even if collected from the post office later. If you live abroad, give an address where someone can sign for it.

The letter states (art. R423-39) that the documents must reach the town hall within three months of its receipt, that if not all of them are supplied the application is tacitly refused (tacitly opposed for a declaration), and that processing starts when they arrive. A second request made within the month replaces the first and restarts the three months (art. R423-40). A request sent after the first month, or for a document the Code does not require, does not change the periods (art. R423-41).

Example: house application filed on 2 March, letter presented on 25 March, last documents received on 20 April. The two-month period runs from 20 April to 20 June.

From filing to the end of the appeal and withdrawal periods: building permit for a single houseThree lines to scale, in months after filing. Complete file: the town hall has one month to ask for a document or notify a longer period; without an extension, the decision or the tacit permit comes at two months, at three months if a one-month extension was notified. Missing documents: the letter arrives at the latest at one month, the applicant has three months from receiving it to send every document, otherwise the application is tacitly refused; the two-month period starts when the documents reach the town hall. After a decision at two months, displayed the same day: two months for third-party appeals from the first day of continuous display, and three months during which an unlawful permit can be withdrawn.0123456months after filingFile complete when filedProcessing: 2 months+1 month if notified1 month: deadline to request documents or extend2 months: written decision or tacit permitMissing documents requestedLetter by month 1 at the latest3 months to send all, or tacit refusal2-month period runsAfter a decision at 2 monthsThird-party appeal: 2 monthsWithdrawal if unlawful: 3 monthsAssumptions: missing-documents letter received at the end of month 1, documents received at the end of the 3 months;decision displayed on site the same day.The appeal period runs from the first day of 2 months of continuous display, and an appeal must be served within 15clear days of filing; the permit generally stays valid for 3 years.
From filing to the end of the appeal and withdrawal periods: building permit for a single houseThree lines to scale, in months after filing. Complete file: the town hall has one month to ask for a document or notify a longer period; without an extension, the decision or the tacit permit comes at two months, at three months if a one-month extension was notified. Missing documents: the letter arrives at the latest at one month, the applicant has three months from receiving it to send every document, otherwise the application is tacitly refused; the two-month period starts when the documents reach the town hall. After a decision at two months, displayed the same day: two months for third-party appeals from the first day of continuous display, and three months during which an unlawful permit can be withdrawn.0123456months after filingFile complete when filed121. Processing: 2 months2. +1 month if notified● 1 month: deadline to request documents orextend● 2 months: written decision or tacit permitMissing documents requested1231. Letter by month 1 at the latest2. 3 months to send all, or tacit refusal3. 2-month period runsAfter a decision at 2 months121. Third-party appeal: 2 months2. Withdrawal if unlawful: 3 monthsAssumptions: missing-documents letter received at theend of month 1, documents received at the end of the 3months; decision displayed on site the same day.The appeal period runs from the first day of 2 monthsof continuous display, and an appeal must be servedwithin 15 clear days of filing; the permit generallystays valid for 3 years.
Timeline for a single house, to scale. A notified extension pushes everything after it back by the same amount. Sources: Planning Code, art. R423-19 to R423-37-3 (processing periods); Planning Code, art. R423-38 to R423-41 (missing documents); Planning Code, art. R600-2; Planning Code, art. L424-5. Accessed 12 November 2026. Version in force on 12/11/2026.

Tacit permit: when silence means yes, and when it means no

If no express decision is notified within the period, silence counts as non-opposition to a prior declaration, or as a tacit permit (art. R424-1). A tacit permit takes effect as soon as it arises (art. L424-8), and the town hall issues a certificate of it on request (art. R424-13), which the bank and the notaire (the notary handling the sale) will want.

Silence means refusal for a permit (art. R424-2, I) for: works needing consent from the defence minister, or consent under the law on classified sites (or sites being classified) or nature reserves; a call-in by the minister for sites or nature reserves; a building on the historic monuments register; a public inquiry (Environment Code art. R123-7 to R123-23) or online public participation; referral to the Corsican Assembly; the core or future core of a national park; a cinema refused by the departmental commission; an unfavourable opinion of the retail planning commission; a demolition in a registered site; a refused exemption under Construction Code art. L111-4-1.

For permits and declarations alike, silence also means refusal if the building is subject to the demolition obligation of art. L121-22-5 (R424-2, II) or the project needs an environmental assessment (R424-2-1). Nor is there a tacit permit where the ABF (architecte des Bâtiments de France, the state heritage architect), whose agreement is required, has notified in time an unfavourable opinion or one with conditions (R424-3). In the R424-2 and R424-2-1 cases, the first-month letter must warn you that silence will mean refusal (art. R423-42).

Warning. An unlawful tacit permit can be withdrawn within three months, like a written one (art. L424-5). It must also be displayed: without display, the third-party appeal period never starts, and only the six-month limit after completion of the works closes the door to appeals (art. R600-3).

Display, appeals, withdrawal and validity

From notification of the decision, or from the day the tacit permit arises, the holder displays the permit on the land, visible from outside, for the whole of the works (art. R424-15).

PeriodLengthStarts fromArticle
Third-party court appeal2 months1st day of two months of continuous display on the landR600-2
Serving the appeal on the holder and the authority15 clear daysfiling of the appealR600-1
Administrative appeal (recours gracieux)1 month, without extending the court deadlinenot set by the article: see the appeal noticeL600-12-2
Withdrawal of an unlawful permit3 monthsdate of the decision, tacit or writtenL424-5
Validity3 years as a general rule; also lapses if, after that period, works stop for more than a yearnotification or date of the tacit permitR424-17
Extensiontwice 1 year, if rules and easements have not changed against the projectapply at least 2 months before expiry; granted if no answer within 2 monthsR424-21 to R424-23

A court appeal suspends validity until a final decision (art. R424-19). Sources: Planning Code, art. R600-2; Service-Public: displaying a planning permission on site; Planning Code, art. R600-1; Planning Code, art. L600-12-2; Planning Code, art. L424-5; Planning Code, art. R424-17 to R424-20 (lapse); Planning Code, art. R424-21 to R424-23 (extension). Accessed 12 November 2026.

A permit the seller already holds: Decree no. 2025-461 covers only authorisations still valid on 27 May 2025, the day it was published (art. 3). Those granted from 1 January 2021 to 27 May 2022 are extended by one year, without the conditions of articles R424-21 to R424-23 (art. 2); those granted from 28 May 2022 to 28 May 2024 are valid for five years, with no extension under the first paragraph of R424-21 (art. 1). For a tacit permit, Service-Public counts validity from filing; article R424-17, which we follow, uses the date of the tacit decision.

What these periods mean for the compromis

In the compromis de vente (the binding preliminary contract), set the date of a permit condition from the period actually notified, not the standard one, with three months’ margin if documents may be requested. If the deed requires a “purged” permit, use the later of two dates: the end of the third-party appeal period (two months of display, plus fifteen clear days to serve an appeal) and the end of the withdrawal period (three months after the decision). The clause itself is covered in our guide to the compromis; before applying, an operational planning certificate states whether the land can be used for the project.

A historic-monument easement (AC1), which can add a month to the period, appears in the annexes of the PLU (the local plan).

In the report: public easements around F 274

Checklist

  • Filing receipt kept, with the tacit-permit date.
  • Letter or not in the first month: documents, longer period, warning that silence will mean refusal.
  • All documents sent together, by recorded delivery, before the three months run out.
  • AC1 easement, classified or registered site, national park: checked before filing.
  • Tacit permit: certificate requested; site notice put up and photographed the same day.
  • Expiry date (general rule or Decree no. 2025-461) and last date to apply for an extension noted.
This guide helps you prepare a purchase and a building project. It is based on the Planning Code in force and on Service-Public, opened on 12 November 2026, and does not replace the town hall, a notaire or a lawyer.

Common questions

Does the processing period start on the day I file?

It starts when the town hall receives a complete file (art. R423-19). If no document is requested within a month of filing, the file counts as complete and the period runs from filing; if documents are requested, it runs from their receipt (art. R423-22 and R423-39).

What if the town hall has not answered after two months?

Check that your case is not one where silence means refusal (art. R424-2, R424-2-1, R424-3) and that no extension letter was presented in the first month. Otherwise the permit is tacit: ask the town hall for a certificate (art. R424-13) and display it on the land.

How long is a French building permit valid?

Three years from notification or from the date of the tacit permit, and it lapses if works stop for more than a year after that (art. R424-17). It can be extended twice by one year, on an application made at least two months before expiry (art. R424-21 and R424-22). That is the general rule: a permit granted from 1 January 2021 to 28 May 2024 and still valid on 27 May 2025 falls under Decree no. 2025-461.

Before you apply, see the easements around the land

Pick the parcel on the map: the report locates published public easements (historic monuments, protected sites, networks), the PLU zone and natural hazards, each with its source and date, explained in English. It does not replace the town hall’s decision. Free preview, PDF report for €29 (€39 in French and English).

The PDF report 29 € incl. VATOrder

Browse a sample report

Cover · F 329, Brailly-Cornehotte
Summary: the purchase decision
Contents
The cadastral parcel
Parcel dimensions
Aerial photographs, 1950–1965
Planning zones around the parcel
Natura 2000 habitat sites
Flood envelope: rivers and run-off
Clay shrink and swell
Overhead power lines
Recorded land sales nearby
What we could not read
Sources and dates