Electricity connection for a bare plot in France: Enedis steps, timings and cost

Utilities, networks and access·14 min read·Updated 12 November 2026

Enedis serves 95% of mainland France excluding Corsica, according to the energy regulator (CRE); elsewhere a local distribution company or, in Corsica and most overseas territories, EDF SEI applies its own rules. With Enedis, a connection of up to 36 kVA with no network extension costs €1,903.68 including VAT after the 40% rebate, under the price list in force since 28 October 2026, and the offer arrives at most three months after the file is accepted as complete. First step: apply online at connect-racco.enedis.fr with a copy of the building permit.

In brief

  • Extension. If the low-voltage network does not reach the plot, Enedis adds a fixed charge and a price per metre: with 50 m of new line in a ZFA zone (outside large urban areas), the bill reaches €7,997.76 including VAT.
  • Who pays for the extension. As a rule, the holder of the building permit or of the non-objection to a prior declaration (Energy Code, art. L342-21). Exceptions apply under conditions (a ZAC or a developer agreement; a permission issued before 10 September 2023 that did not put the extension on the applicant, for the part beyond the plot): see who pays for the extension.
  • Timeline. The offer is valid for three months, your works on the plot are due within the three months it sets, then come Enedis’s works on the timing stated. The law sets no maximum period for a house.
  • Your share. Trench, duct and cabinet recess on your land, on a contractor’s quote, then a Consuel certificate (electrical safety sign-off) where required.
On this page

Enedis or another operator

According to the energy regulator (CRE), Enedis and some 160 municipal or local distribution companies (entreprises locales de distribution, ELD) share the public distribution networks. Enedis serves 95% of mainland France excluding Corsica; EDF SEI serves Corsica and most overseas territories. Each operator has its own method for pricing connections, approved by the CRE above 100,000 customers (art. L342-19).

Prices, timings and forms in this guide are Enedis’s. If the commune is served by an ELD, such as SER in Strasbourg or GEG in Grenoble, ask for its own procedure and price list.

Sources: Energy regulator (CRE): electricity networks; Energy Code, art. L342-19. Accessed 12 November 2026.

Applying: where, when, with which documents

For a single installation of up to 36 kVA, you apply online at connect-racco.enedis.fr, in French; private individuals without internet access may apply by post. The form requires the street number and name and the cadastral reference, plus a location plan, a site plan showing the cabinet, a photograph, a cadastral plan and a full copy of the planning permission. A plot with no street number gets one from the mairie (town hall): see the certificat de numérotage.

Enedis encourages you to apply “as soon as you own your plot”, but the request is only complete with a copy of the permit or non-objection where the project needs one. If an extension is needed, the price list offers an early request: an offer before the file is complete, against an advance of €608.40 including VAT.

Steps and how long each takes

  1. Apply online. Enedis confirms when the file is complete. Nothing to pay yet, except the advance for an early request.
  2. Connection offer at most three months after the file is accepted; Enedis says it can be six weeks for a house and ten working days for a service connection alone.
  3. Acceptance within the three months the offer is valid, with a deposit: the whole amount up to €2,000 including VAT, half between €2,000 and €10,000. With no answer, the offer lapses.
  4. Your preparatory works on the plot, within the three months set in the offer. Cost: your contractor’s quote.
  5. Enedis’s works: the expected time is in the offer and runs from acceptance. Ground, weather or supply problems can stretch it.
  6. Switch-on once the final invoice is paid, the Consuel certificate is in where required and your supplier has asked for it; done remotely with a smart meter.

The Energy Code sets maximum periods for some generating plants, charging points and radio masts (art. L342-8 to L342-9-1), not for a house.

Sources: Enedis: connection request form up to 36 kVA, Enedis-MOP-RAC_003E (3 July 2025); Enedis: procedure for connection requests up to 36 kVA, Enedis-NMO-RAC_006E (3 July 2025); Enedis: connection works for your house or premises up to 36 kVA (October 2025); Energy Code, art. L342-1 to L342-25 (connection to the networks). Accessed 12 November 2026.

Service connection or extension: the bill

A connection combines, depending on the case, an extension, a low-voltage service connection (branchement) and network reinforcement (art. L342-1). The service connection links your cabinet to the network running past the plot. Where that is not possible, Enedis builds an extension up to the main isolating fuse (CCPI) in the cabinet.

There are two layouts. Type 2: meter and breaker in a cabinet on the property line. Type 1: meter inside the house, allowed only if the cable on private land is under 30 m.

Price list itemPrice incl. VATAfter rebateNote
Complete service connection, type 1 or 2€3,172.80€1,903.68Excludes trench and duct on your land
Public-land section only€2,648.40€1,589.04Case named: servicing a bare plot
Private-land section only€802.80€481.68Case named: a plot in a subdivision
Extension in ZFA€3,316.80 + €136.80/m€1,990.08 + €82.08/mSubstation within 250 m
Extension in ZFB€4,288.80 + €180.00/m€2,573.28 + €108.00/mSubstation within 250 m

Enedis price list version 8, in force since 28 October 2026, up to 36 kVA, VAT at 20%. ZFB: urban units of over 100,000 people and Paris; ZFA: everywhere else. Beyond 250 m from the substation, the bill can include a transformer substation. Sources: Enedis: connection price list, Enedis-NMO-RAC_009E, version 8 in force from 28 October 2026 (approved by the CRE on 28 July 2026); CRE decision no. 2026-160 of 28 July 2026 approving Enedis’s connection price list; Order of 30 November 2017 on the share of connection costs covered by network tariffs, art. 1. Accessed 12 November 2026.

Worked example: ZFA zone, 50 m of new line. Service connection: 3,172.80 × 60% = €1,903.68. Extension: (3,316.80 + 50 × 136.80) × 60% = €6,094.08. Total: €7,997.76 including VAT, with a €3,998.88 deposit. The 40% rebate (réfaction) is the share paid through network tariffs: capped at 40% by law (art. L342-11) and set at 40% by the order of 30 November 2017.

Contribution billed by Enedis by length of new networkComplete service connection plus low-voltage extension, after the 40% tariff rebate, in euros including VAT, Enedis price list version 8. No extension: 1,904 euros in both zones. 25 metres: 5,946 in ZFA, 7,177 in ZFB. 50 metres: 7,998 and 9,877. 100 metres: 12,102 and 15,277. 150 metres: 16,206 and 20,677.ZFA: communes outside large urban unitsZFB: urban units over 100,000 people€1,904€1,904none€5,946€7,17725 m€7,998€9,87750 m€12,102€15,277100 m€16,206€20,677150 mmetres of new low-voltage line
Contribution billed by Enedis by length of new networkComplete service connection plus low-voltage extension, after the 40% tariff rebate, in euros including VAT, Enedis price list version 8. No extension: 1,904 euros in both zones. 25 metres: 5,946 in ZFA, 7,177 in ZFB. 50 metres: 7,998 and 9,877. 100 metres: 12,102 and 15,277. 150 metres: 16,206 and 20,677.ZFA: communes outside large urban unitsZFB: urban units over 100,000 peoplenone€1,904€1,90425 m€5,946€7,17750 m€7,998€9,877100 m€12,102€15,277150 m€16,206€20,677metres of new low-voltage line
Complete service connection plus extension, after the rebate, substation within 250 m. TerrainCheck calculation from Enedis price list version 8, approved by the CRE on 28 July 2026, rounded to the euro. Works on your own land not included. Sources: Enedis: connection price list, Enedis-NMO-RAC_009E, version 8 in force from 28 October 2026 (approved by the CRE on 28 July 2026); CRE decision no. 2026-160 of 28 July 2026 approving Enedis’s connection price list; Order of 30 November 2017 on the share of connection costs covered by network tariffs, art. 1. Accessed 12 November 2026.

The amount in the offer stays firm if all the planned works are finished within six months of the offer being sent or posted in your Enedis online account. If the works have to continue beyond that for reasons outside Enedis’s responsibility and control, the amount is revised in line with the price list then in force, less the deposit paid when you accepted the offer (Enedis procedure, section 7.2.4.5). A delay caused by Enedis does not trigger this revision.

Who pays for the extension

The person requesting the connection owes the contribution (art. L342-21). An extension made necessary by a building permit, a development permit or a non-objection to a prior declaration is paid by the holder of that permission, outside a ZAC (planned development zone) and outside the planning levies the law names.

Enedis applies one exception: a permission issued before 10 September 2023 that did not put the extension on the applicant. The part beyond the plot then falls to the commune or its grouping of communes. In a ZAC or under a developer agreement, the developer may owe it.

Buying a plot with a permit the seller obtained? Note when it was issued, what it says about utilities and how long it lasts: see building permit timings and validity.

Sources: Energy Code, art. L342-21; Enedis: procedure for connection requests up to 36 kVA, Enedis-NMO-RAC_006E (3 July 2025). Accessed 12 November 2026.

On your land: trench, duct, cabinet

The recess or plinth for the cabinet, the trench, ducts and wall openings are preparatory works at your cost, outside Enedis’s offer: get a quote from a groundworks firm or your house builder. For type 1, Enedis asks for a 75 mm TPC duct in a trench at least 65 cm deep, red warning mesh 20 cm above, and pulls the cable through. For type 2, the cable from the breaker to your consumer unit is part of your own installation (NF C 15-100 wiring standard).

From the network to the meter: who does whatEnedis builds the existing network, any extension and the cabinet on the property line. On the plot, the trench, the duct and the recess for the cabinet are the applicant’s. Type 2: meter in the boundary cabinet, cable to the house by your electrician. Type 1: meter in the house, cable laid by Enedis in your duct, if the private section is under 30 metres.PUBLIC LANDYOUR PLOTproperty lineExisting networkEnedisExtensionif the networkdoes not reachCabinet + CCPIfitted by EnedisAs a rule, the extension is paid bythe permit holder (L342-21).Exceptions apply under conditions: seethe section “Who pays for the extension”.Type 2meter and breakerin the boundary cabinetcable to the house:your electrician (NF C 15-100)Type 1meter in the housecable laid by Enedisin your 75 mm TPC ductif under 30 m on your landYou: trench, duct, recess or plinth for the cabinet
From the network to the meter: who does whatEnedis builds the existing network, any extension and the cabinet on the property line. On the plot, the trench, the duct and the recess for the cabinet are the applicant’s. Type 2: meter in the boundary cabinet, cable to the house by your electrician. Type 1: meter in the house, cable laid by Enedis in your duct, if the private section is under 30 metres.PUBLIC LANDExisting networkEnedisExtensionif the networkdoes not reachAs a rule, the extension is paid bythe permit holder (L342-21).Exceptions apply under conditions: seethe section “Who pays for the extension”.Cabinet + CCPIfitted by Enedisproperty lineYOUR PLOTType 2meter and breakerin the boundary cabinetcable to the house:your electrician (NF C 15-100)Type 1meter in the housecable laid by Enedisin your 75 mm TPC ductif under 30 m on your landYou:trench, duct, recess or plinth for the cabinet
Who does which works for a single connection of up to 36 kVA with Enedis. Diagram not to scale. Sources: Enedis: connection price list, Enedis-NMO-RAC_009E, version 8 in force from 28 October 2026 (approved by the CRE on 28 July 2026); Enedis: procedure for connection requests up to 36 kVA, Enedis-NMO-RAC_006E (3 July 2025); Enedis: connection works for your house or premises up to 36 kVA (October 2025); Energy Code, art. L342-21. Accessed 12 November 2026.

The law also lets you hire a firm approved by Enedis, at your cost, for the parts serving only your installation; Enedis must accept them before switch-on (art. L342-6).

Sources: Enedis: procedure for connection requests up to 36 kVA, Enedis-NMO-RAC_006E (3 July 2025); Enedis: connection works for your house or premises up to 36 kVA (October 2025); Energy Code, art. L342-6. Accessed 12 November 2026.

Power during the build

With Enedis, a temporary building-site supply lasting over 28 days, up to 36 kVA and needing only connection work, costs €536.40 including VAT for a “non-fixed” connection (no connection point on the ground), €400.80 for a “semi-equipped non-fixed” one (a low-voltage network unit is already fixed in the ground) and €43.20 for a “fixed” one, for example on a meter cabinet already installed on the plot boundary, switched on remotely. These prices include the 40% rebate; the customer provides the cable and cabinet. If the network has to be extended to reach the site, the extension is billed on top, on an Enedis quote (price list, sections 13.1.1 and 13.2).

Watch out. These amounts apply to Enedis’s reference solution. Any variant you ask for (another route, the meter elsewhere) costs extra. If you pull out after accepting, the costs incurred are billed without the rebate, less your deposit.

Sources: Enedis: connection price list, Enedis-NMO-RAC_009E, version 8 in force from 28 October 2026 (approved by the CRE on 28 July 2026); Enedis: connection works for your house or premises up to 36 kVA (October 2025); Enedis: procedure for connection requests up to 36 kVA, Enedis-NMO-RAC_006E (3 July 2025). Accessed 12 November 2026.

In the report: high-voltage lines near F 274

Before the compromis: six checks on electricity

  • Network operator for the commune identified: Enedis or an ELD.
  • Street number and cadastral reference ready for the form.
  • Permit: issue date and conditions on utilities noted.
  • Likely extension checked with Enedis, by an early request if needed.
  • Trench, duct, cabinet and site supply quoted.
  • Compromis de vente (preliminary contract): who pays for connection and extension, in writing.

Read next: serviced or unserviced plot and the clauses of the preliminary contract.

This guide helps you prepare a purchase. It is based on public sources opened on 12 November 2026 and does not replace the network operator’s connection offer or the notaire.

Common questions

How much does an Enedis connection cost for a new house?

Under the price list in force since 28 October 2026, a complete service connection up to 36 kVA costs €1,903.68 including VAT after the 40% rebate, if no extension is needed. With an extension, add your zone’s fixed charge and price per metre: in ZFA, 50 m of new line brings the total to €7,997.76. The trench and duct on your land are extra, on a contractor’s quote.

Can I apply before I have the building permit?

You can file the request, but it is only complete with a copy of the planning permission where the project needs one, and the clock for the offer starts when the file is accepted as complete. For a project needing an extension, an early request gives you an offer before completion, against an advance of €608.40 including VAT.

Does the commune pay for extending the network?

As a rule, no: the holder of the permit or non-objection pays (Energy Code, art. L342-21). Enedis bills the commune or its grouping, for the part beyond the development site, only if the permission was issued before 10 September 2023 without putting the extension on the applicant.

How long does it take to get connected?

With Enedis: an offer at most three months after the file is accepted (six weeks or ten working days possible, Enedis says), three months to accept it, at most three months for your preparatory works, then the works period stated in the offer. The law sets no maximum period for connecting a house.

Before pricing the connection, look at the plot

Pick the parcel on the map. The report shows the overhead power lines published by IGN, road access, the PLU planning zone and natural hazards, each with its source and date, explained in English. It does not replace Enedis’s study of the low-voltage network. Free preview, PDF report for €29 (€39 in French and English).

The PDF report 29 € incl. VATOrder

Browse a sample report

Cover · F 329, Brailly-Cornehotte
Summary: the purchase decision
Contents
The cadastral parcel
Parcel dimensions
Aerial photographs, 1950–1965
Planning zones around the parcel
Natura 2000 habitat sites
Flood envelope: rivers and run-off
Clay shrink and swell
Overhead power lines
Recorded land sales nearby
What we could not read
Sources and dates